The main classroom block roof at the village primary school has been leaking for two monsoon seasons, forcing 65 children to be crowded into two smaller rooms during heavy rain. This project replaces the damaged roofing sheets and repairs the supporting timber frame.
Roofing materials for half the block have been purchased and installed. Remaining sheets are being sourced; carpentry work continues as funds allow.
| Item | Est. Cost | Actual To-Date | Support Received | Balance Reqd. |
|---|---|---|---|---|
| Material (BOQ attached) | 56,300 | 42,500 | 42,500 | 13,800 |
| Specialised / skilled labor | 21,700 | 16,300 | 16,300 | 5,400 |
| Transport | 10,400 | 7,800 | 7,800 | 2,600 |
| Labor man-days | 15,600 | 11,800 | 11,800 | 3,800 |
| Special items | 17,300 | 13,100 | 13,100 | 4,200 |
| Other minor costs | 8,700 | 6,500 | 6,500 | 2,200 |
| TOTAL | LKR 130,000 | LKR 98,000 | LKR 98,000 | LKR 32,000 |
| Date | Patron | Type | Amount (LKR) | Notes |
|---|---|---|---|---|
| — | Colombo Rotary Club | Organization | 90,000 | |
| — | A. Wijesinghe | Individual | 8,000 | |
| TOTAL RECEIVED | 98,000 | |||